PROJECTS
CEMENT PLANTS
 
List of Projects Completed
Name of the Projects/Client
Manhours
Status of Projects
Duct Supports, Platforms & various modifications for LES CIMENTS DU SAHEL S.A. Kirene, Geneva (with EURO / DIN CODES)
1400 Manhours
Completed
Roller Press Building for Southern Province Cement Company at Bisha, Saudi Arabia.(With EURO, DIN & UBC codes)
1500 Manhours
Completed
Raw Mill Building for Pennsuco Cement Company at Medley, Florida, USA, this job is given by F. L. SMIDTH USA. (As per American codes)
5500 Manhours
Completed
Raw material hopper building for Peennsuco Cemetn Company, Medley Florida, USA, this job is given by F. L. SMIDTH. (As per American codes)
4000 Manhours
Completed
Deep Bucket Conveyor system for Clinker Handling system for Pennsuco Cement Company at Medley, Florida, USA. This job is given by F. L. SMIDTH. (As per American Codes)
2200 Manhours
Completed
Secondary Crusher Building for Peennsuco Cement Company, Medley Florida, USA, this job is given by F. L. SMIDTH. (As per American codes)
1500 Manhours
Completed
Shed over clinker silo supporting DBC and tall bucket elevator structure for Pennsuco Cement Company, Medley Florida, USA, this job is given by F.L.SMIDTH. (As per American codes)
1200 Manhours
Completed
Estimation of detailed bill of material for Raw mill building, Raw mill feed bins, secondary crusher, DBC, transfer towers etc. for Pennsuco Cement company, Medley Florida, this job is given by F.L.SMIDTH.
700 Manhours
Completed
Raw mill feed tower structure for Algerian Cement Company at M’Sila, Algeria. This job is given by F. L. SMIDTH. (As per Euro & Algerian codes). This job involves bar bending schedule and all connection designs.
2000 Manhours
Completed
Airlift tower structure for Algerian Cement Company at M’Sila, Algeria. This job is given by F. L. SMIDTH. (As per Euro & Algerian codes). This job involves bar bending schedule and all connection designs.
1100 Manhours
Completed
Cable tunnels / pits for complete plant for Algerian Cement Company at M’Sila, Algeria. This job is given by F. L. SMIDTH. (As per Euro & Algerian codes). This job involves bar bending schedule and all connection designs.
1200 Manhours
Completed
Weight bridges / control rooms for Algerian Cement Company at M’Sila, Algeria. This job is given by F. L. SMIDTH. (As per Euro & Algerian codes). This job involves bar bending schedule and all connection designs.
450 Manhours
Completed
Preparation of Detailed Fabrication drawings for HAI-PONG Cement Company at Vietnam, this job is given by F. L. SMIDTH (As per Euro Codes).
12000 Manhours
Completed
6 Substation structures for AUCC Libya Cement Project for F. L. SMIDTH, this is done as per BS codes.
6000 Manhours
Completed
Cable tunnels for complete AUCC Libya Cement Project for F. L. SMIDTH, this is done as per BS codes.
2000 Manhours

 

Laboratory building, control rooms, weight bridges, Storage hall for AUCC Libya Cement Project for F. L. SMIDTH, this is done as per BS codes.
2500 Manhours
Completed
Preheater tower, Cooler Buildng for Chaibasa Cement plant for ACC
2500 Manhours
Completed
3D analysis and computation of loads for very large ducts for GULF CEMENT project a UAE. This is a very specialized project.
1800 Manhours
Completed
Close Circuiting of Cement Mill at Burkina Faso, West Africa for VOLTA IMPEX
1800 Manhours
Completed
 
List of Projects In Hand
Name of the Projects/Client
Manhours
Status of Projects
UCC CALABAR CEMENTS NIGERIA
Various structures like Compressor houses, Oil storage areas, misc. structures, cable tunnels etc. AS PER BS CODAL PROVISION
6000 Manhours
50% complete
GULF CEMENTS 40 M tall chimneys for COOLER AREA and BAG HOUSE AREA including fab. Drgs. And very complicated duct supporting structures in raw mill area.
1200 Manhours
90% complete
Halong I & II at Vietnam, Cement mill, for FLS.
2000 Manhours
Just started
Preparation of Bar Bending Schedule for D.G. Building as per British Standard norms in AutoCAD for Benue Cement Company, Yandev, NIGERIA
1000 Manhours
90% Complete
 
Indian Projects
 
Name of the Project / Client
Manhours
Status of
Project
1.2 MTPA Cement plant for Associated Cement Companies (A.C.C.) at Kymore. Silos, Coal Mill building, Cooler Bldg., Chimneys, Preheater Tower Chimney, Deep Bucket conveyor etc.
4500 Manhours
Completed
Complete Expansion and Modifications for KESORAM CEMENT, at Basantnagar.
3000 Manhours
Completed
Expansion / Modifications of Cement plant for WADI CEMENT WORKS for the Associated Cement Companies Limited.
2000 Manhours
Completed
Expansion/Modifications of Cement plant for CHANDA CEMENT WORKS,for Associated Cement Companies.
900 Manhours
Completed
1 M.T.P.A. Cement plant – additions / modifications for Associated Cement Companies at GAGAL, Himachal Pradesh.
1000 Manhours
Completed
Modifications and Strengthening of Structures, like Kiln Feed Building, silos etc. for Penden Cement, Bhutan.
700 Manhours
Completed
Flyash Silo, Duct Supports for A.C.C. Kymore Cement plant.
950 Manhours
Completed
Duct Supporting Structures for Penden Cement Bhutan.
250 Manhours
Completed
Bhupendra Cement WorksBag Filter Supporting Structures, duct supporting structures, chimneys etc.
900 Manhours
Completed
Lakheri Cement works. Bag Filter Supporting Structures, duct supporting structures, chimneys etc.
850 Manhours
Completed
Modifications in Cement Silo for Penden Cement Bhutan.
300 Manhours
Completed
Extg. ESP modifications by putting new bag filter, cyclone building and Shed over Raw mill fan.Checking of Fab. Drawings.
1200 Manhours
Completed
Secondary Crusher building, checking of shuttering of preheater tower and strengthening of the same, 50M high Tower structure etc.
900 Manhours
Completed
Modifications for two preheaters and doing the detailed Analysis and design of two preheaters for Rajashree Cements.
300 Manhours
Completed
Wagon Tippler for ACC Wadi.
1250 Manhours
Completed
Modifications/Expansion of Cement plant At Chaibasa for Associated Cement Companies.
1500 Manhours
Completed
DBC for the Associated Cement Companies Limited, Chaibasa.
600 Manhours
Completed
Platform structure for Kiln Erection for The Associated Cement Companies, CHAIBASA
300 manhours
Completed
Cement Mill, Packing Plant, Hopper Building, Fly ash handling system, Truck Tippler etc. for Gujarat Ambuja Cements at Ropar
4500 Manhours
Completed
30m Wide x 96M long Gypsum Storage Shed for Gujarat Ambuja’s Gajambuja Cement plant at Kodinar.
900 manhours
Completed
Extension of Shovel Repair Shed at Wadi Cement works for The Associated Cement Companies.
300 Manhours
Completed
Extension of gantry shed 23M x 53M long for Associated Cement Companies, Madukkarai Cement works.
450 Manhours
Completed
Tertiary Crusher building for Associated Cement Companies, Chanda Cement works.
550 Manhours
Completed

Bucket elevator structure near cement silos, and blending silos (2 nos.) along with modifications and strengthening for Associated Cement companies, Gagal cement works.

1200 Manhours
Completed
Bucket Elevator structure for Raw mill structure at Gagal Cement works for ACC.
300 Manhours
Completed
Bucket Elevator structures (4 Nos.) of Kymore Cement works for ACC.
1000 Manhours
Completed
Modification works for Gagal Cement works for ACC, Precipitator structure, Bucket elevator structures, HRP modifications, Cement Mill modifications etc.
2000 Manhours
Completed
CLINKER COOLER BUILDING for HOLTEC for their Cement Plant in Costa Rica with FCB
3000 Manhours
Completed
55M Tall Transfer Tower for ACC at Gagal
700 Manhours
Completed
Modifications and augmentation job for Birla Cement works and Chittor Cement works, Petcoke structure, Conveyor Galleries, Flyash Handling systems etc.
2000 Manhours
Completed
Preheater tower for Lakshmi Cement at Sirohi.
3300 Manhours
Completed
Proposed Screen & Secondary Crusher Instalation at Kashlog Darlaghat, for Gujarat Ambuja Cement Limited
1800 Manhours
Completed
Proposed installation of Cross belt Analyser Structure at existing LSH-09 Conveyor for the Kymore Cement Works
400 Manhours
Completed
Very special Transfer tower receiving 4 DPCs, 75M Tall for ACC
800 Manhours
Completed
30m wide storage shed at Tikaria Cement works for ACC
300 Manhurs
Completed
GACL’s Bhatinda jobVarious air slide galleries and misc. structures like BE structures, ground structures etc.
500 Manhours
Completed
 
List of Projects In Hand
 
Name of the Project / Client
Manhours
Status of
Project
Tertiary Crusher Building at Kymore
400 Manhours
25% complete
RAS CEMENT WORKS
Preheater Tower, Clinker Grinding unit, DBC and Primary Crusher structure, DUMP hopper area, conveyors, raw mill ducting, hopper structurces, DBC etc.
9000 Manhours
95% complete
VASVADATTA CEMENTS
Compete pyro section, Preheater tower, Kiln piers, cooler building, TA ducts etc.
6000 Manhours
80% complete
5200 Gagal Modernization Project for Packer Building & Cooler Modification work for ACC
800 Manhours
90% complete
Cooler modification Project and duct modification job for Ambuja Cement Rajasthan
600 Manhours
Just Started
 
Designed & Developed by Sanmisha Technologies